Client case study
Packaging manufacturer NSW
CLIENT: Visy
PROJECT TYPE: Energy Performance Contract
Industry: INDUSTRIAL
Status: COMPLETED
the challenge
As we see on many industrial sites, this facility is constantly changing in its operations and production requirements. Over the course of a few months, the production profile of several departments shifted as new orders were secured – shifting those departments from 24/5 operation to 24/7. This presented challenges in implementing solutions such as securing a production window for outage works, as well as in the final savings values.
The solution
The new work packages were delivered within the original budget and the savings achieved, as well as securing the funding. Investigations using CoolPlanet OS data also identified a significant failure inside a relatively new air compressor on site.
The results
The new work packages were delivered within the original budget and the savings achieved, as well as securing the funding. Investigations using CoolPlanet OS data also identified a significant failure inside a relatively new air compressor on site.
- Implementation of Clarity data analytics to measure and validate the achieved energy savings
- Compressed air optimisation
- Potential NSW Department of Planning and Environment funding for the project